DISUSUN OLEH;…………………
KELAS XTGB 1
MENGHITUNG BIAYA PONDASI
Ø L1= (a+b)X t/2=(30+80)x80/2= 4.400 cm2 =0,44 m2
Ø L2=pxl = 100x10 =1.000 cm2 = 0,1 M2 +
0,54 m2
Ø VOLUME PONDASI = 0,54 M2 x 1 M=0,54 M3
Ø PANJANG PONDASI =45,5 M
Ø VOLUME PONDASI KESELURUHAN = 45,5M X 0,54M3 = 24,57 M3
Ø MENCARI VOLUME BATU PECAHAN = 70% X 24,57 M3 = 17,2 M3
Ø HARGA BATU PECAHAN /M = Rp.200.000 X17,2M3 = Rp.3.440.000
Ø MENCARI VOLUME PASIR = 30% X 24,57 M3 =7,4 M3
Ø HARGA 1 TRUK PASIR = Rp.650.000 X 2 TRUK = Rp.1.300.000
Ø
Ø HARGA 1 ZAK SEMEN GRESIK = Rp.50.000 /40 kg x 40 ZAK = Rp.2.000.000
Ø
Ø HARGA 1 KW GAMPING= Rp.180.000 X5 KW = Rp.900.000
Ø BIAYA TUKANG DAN KULI
Ø 2 TUKANG X Rp.60.000X14 HARI = Rp.1.680.000
Ø 4 KULI X Rp.50.000X14 HARI = Rp.280.000+
= Rp.12.120.000
Ø BIAYA TAK TERDUGA 10% X Rp.12.120.000 = Rp.1.212.000
v TOTAL = Rp.13.332.000
BIAYA PEKERJAAN DINDING
Ø PANJANG PONDASI 45,5 M X4M X60 BIJI = 10.920 BIJI
Ø HARGA BATU BATA Rp.480.000 /1.000 BJI
Rp.480.000 X10.920 /1.000 = Rp.5.241.600
Ø PASIR PASANG Rp.650.000 /4,5 = 1 TRUK
Rp.650.000 X 3 TRUK = Rp.1.950.000
Ø SEMEN GRESIK Rp.50.000 /kg
Rp.50.000 X 14 ZAK = Rp.700.000
Ø HARGA 1 KW GAMPING Rp.180.000
Rp.180.000 x5 kw = Rp.900.000
Ø DIKERJAKAN 2 TUKANG X Rp.60.000 X 40 HARI = Rp.4.800.000
Ø DIKERJAKAN 4 KULI X Rp.50.000 X 40 HARI = Rp.8.000.000+
Rp.12.265.000
Ø BIAYA TAK TERDUGA 10% X RP.12.265.000 = RP.1.226.500
v TOTAL = Rp.13.491.500
BIAYA RENCANA TERAS , PLAT ,INTERNIT
TERAS DAN PLAT
Ø LUAS SELURUH TERAS 8M2
Ø LUAS SELURUH PLAT 5M2
Ø HARGA 1TRUK PASIR RP.600.000 X 1TRUK = RP.600.000
Ø BESI 10**= 13 BATANG X RP.35.000 = RP.455.000
BESI 6** = 2 BATANG XRP.20.000 = RP.40.000
BESI 8** = 6 BATANG X RP.25.000 = RP.150.000
Ø LISPLANG COR =RP .300.000
Ø HARGA TIANG RP.300.000 X 2 BUAH = RP.600.000
Ø ASBES 4 LEMBAR X RP. 50.000 = RP.200.000
Ø KAYU 6/ 12 3 BATANG X RP. 150.000 = RP.450.000
Ø SEMEN GRESIK 8 ZAK X RP.50.000 =RP.400.000
INTERNIT
Ø INTERNIT 1 LEMBAR /1 M2 X 70M2
Ø HARGA 1 LEMBAR INTERNIT RP.9.000 X 70 LEMBAR = RP.630.000
Ø KAYU MERAN TI 4/6 RP.46.000 X 90 BATANG = RP.4.140.000
Ø KAYU MERANTI 2/3 25 BIJI = RP.280.000
Ø PAKU INTERNIT = 2 Kg X RP.25.000 = RP.50.000
Ø PAKU USUK = 5 Kg X RP.25.000 = RP.125.000
Ø PAKU RENG = 3 Kg X RP.25.000 = RP.75.000
Ø DIKERJAKAN 2 TUKANG X RP.60.000 X 14 HARI = RP.1.680.000
Ø DIKERJAKAN 3 KULI X RP.50.000 X 14 HARI = RP.2.100.000+
RP.11.665.000
Ø BIAYA TAKTERDUGA 10% X RP.11.665.000 = RP.1.166.500
v TOTAL = RP.12.831.500
BIAYA RENCANA ATAP DAN KUDA –KUDA
Ø KAYU UNTUK KUDA – KUDA ,MERANTI 6/ 12
KAKI KUDA 3 BATANG
SOKONG 1 BATANG
TIANG 1 BATANG+
7 BATANG
Ø HARGA KAYU 6/12 .400
Ø KEBUTUHAN 3 KUDA –KUDA = 3 X 7BATANG X RP. 150.000 = RP.3.150.000
Ø BALOK TEMBOK 9 BATANG X RP. 150.000 = RP.1.350.000
Ø GOERDING 6 BATANG X RP.150.000 = RP. 900.000
Ø JURAI LUAR DAN DALAM 10 BATANG X RP. 150.000 = RP. 1.500.000
Ø BALOK BUBUNGAN 2 BATANG X RP.150.000 = RP.300.000
Ø KAYU MERANTI 5/7 .400 RP. 70.000
Ø USUK MEMBUTUHKAN 90 BATANG X RP.70.000 = RP. 6.300.000
Ø KAYU MERANTI 2/3 .400 RP 13.000
Ø RENG MEMBUTUHKAN 100 BATANG X RP.13.000 = RP.1.300.000
Ø KAYU MERANTI 3/25 .400 RP.150.000
Ø PAPAN LISPLNG MEMBUTUHKAN 8 BATANG XRP.150.000 = RP.1.200.000
PAKU
Ø PAKU 5** = 9 Kg X RP.25.000 = RP.225.000
Ø PAKU 3** = 9 Kg X RP.25.000 = RP.225.000
Ø PAKU 2** = 4 Kg x RP.25.000 = RP.100.000
GENTENG
Ø GENTENG M CLAS RP.2000/ BUAH
Ø LUAS ATAP 86 M2
86 M2 X 20 BUAH / M2 = 1.720 BUAH
JADI GENTENG YANG DI BUTUHKAN = 1.720 X RP .2000 = RP.3.440.000
Ø GENTENG BUBUNGAN 5 BUAH /M
34 M X 5 BUAH = 170 BUAH X RP.3.500 = RP.595.000
Ø SEMEN GRESIK RP 50.000 /40 Kg
MEMBUTUHKAN 3 ZAK X RP.50.000 = RP.150.000
Ø DIKERJAKAN 3 TUKANG X RP.70.000 X 30 HARI = RP.6.300.000
Ø DIKERJAKAN 4 KULI X RP.50.000 X 30 HARI = RP. 6.000.000+
= RP.33.035.000
Ø BIAYA TAKTERDUGAH 10% X RP.33.035.500 = RP.3.303.500
v TOTAL = RP.36.338.500
BIAYA RENCANA UBIN
TEGEL
Ø LUAS YANG HARUS DI TEGEL ADALAH 70 M2
Ø HARGA TEGEL RP.45.000 /M2 X 70 = RP.3.150.000
Ø MEMBUTUHKAN PASIR 1 TRUK
HARGA 1 TRUK PASIR RP.650.000 X 1 TRUK = RP.650.000
Ø GAMPING MEMBUTUHKAN 1 KW
HARGA 1 KW GAMPING RP.180.000 X 1 KW = RP.180.000
Ø MEMBUTUHKAN 10 ZAK SEMEN
HARGA 1 ZAK SEMEN RP.50.000 X 10 ZAK = RP.500.000
Ø DIKERJAKAN 1 TUKANG X RP.60.000 14 HARI = RP.840.000
Ø DIKERJAKAN 1 KULI X RP.45.000 X 14 HARI = RP.630.000+
= RP.5.950.000
Ø BIAYA TAK TERDUGA 10% X RP.5.950.000 = RP.595.000
v TOTAL RP.6.545.000
BIAYA PEMBUATAN KUSEN
MENGGUNAKAN KAYU KAMPER
v KEBUTUHAN KUSEN
Ø PANJANG KUSEN PINTU & JENDELA UTAMA = 16,16 M
Ø HARGA KUSEN PINTU 7 JENDELA UTAMA RP.2.100.000 X 1 BUAH = RP.2.100.000
Ø PANJANG KUSEN PINTU 1 = 4,92 M X 2 BUAH = 9,84 M
PANJANG KUSEN PINTU 2 = 4,92 M X 1 BUAH = 4,92 M
PANJANG KUSEN PINTU 3 = 4,92 M X 1 BUAH = 4,92 M+
19,68 M
Ø HARGA KUSEN PINTU = RP.300.000 X 4 BUAH = RP.1.200.000
Ø PANJANG JENDELA 1 = 7,14 M X 2 BUAH = 14,28 M
PANJANG JENDELA 2 = 4,44 M X 6 BUAH = 26,64 M
PANJANG JENDELA 3 = 3,24 M X 2 BUAH = 6,48 M+
47,4 M
Ø HARGA KUSEN JENDELA 1 = RP.300.000 X 2 BUAH = RP.600.000
Ø HARGA KUSEN JENDELA 2 = RP.250.000 X 6 BUAH = RP.1.500.000
Ø HARGA KUSEN JENDELA 3 = RP.250.000 X 2 BUAH = RP.500.000+
RP.5.900.000
v KEBUTUHAN DAUN PINTU DAN JENDELA
Ø DAUN PINTU & JENDELA UTAMA 1 BUAH XRP.2.500.000 = RP.2.500.000
Ø DAUN PINTU 4 BUAH X RP.600.000 = RP.2.400.000
Ø DAUN JENDELA 1 = 2 BUAH X RP.550.000 = RP.1.100.000
DAUN JENDELA 2 = 6 BUAH X RP.500.000 =RP.3.000.000
DAUN JENDELA 3 = 2 BUAH X RP.500.000 = RP.1.000.000+
RP.10.000.000
v TOTAL KESELURUHAN = RP.15.900.000
BIAYA PENGECATAN
Ø LUAS TEMBOK YANG HARUS DI CAT 486 M2
Ø MEMBUTUHKAN 2 ZAK KALSIUM
HARGA 1 ZAK KALSIUM /40Kg = RP.25.000 X 2 ZAK = RP.50.000
Ø MEMBUTUHKAN 1 ZAK SEMEN PUTIH
HARGA 1 ZAK SEMEN PUTIH /40Kg = RP.60.000 X 1 ZAK = RP.60.000
Ø MEMBUTUHKAN 2 DUS LEM RAJAWALI
HARGA LEM RAJAWALI 1 DUS/10 BIJI = RP.100.000 X 2 DUS = RP.200.000
Ø MEMBUTUHKAN 6 PEL CAT TEMBOK MERK PARAGON
HARGA 1 PEL CAT /20 Kg = RP.250.000 X 6 PEL CAT = RP.1.500.000
Ø UNTUK MENGECAT MEMBUTUHKAN 2 ROLL X RP.25.000 = RP.50.000
Ø DIKERJAKAN 2 TUKANG X RP.60.000 X 15 HARI = RP.1.800.000+
RP.3.660.000
Ø BIAYA TAK TERDUGA 10% X RP.3.660.000 = RP.366.000
v TOTAL = RP.4.026.000
BIAYA SALURAN AIR BERSIH DAN KOTOR
Ø BATU BATA MEMBUTUHKAN 1.500 BIJI
HARGA BATU BATA = RP.500.000 X 1.500/1.000 BIJI = RP.750.000
Ø SEMEN GRESIK MEMBUTUHKAN 5 ZAK /40Kg X RP.50.000 = RP.250.000
Ø RESAPAN 3 BETON BES X RP.50.000 = RP.150.000
Ø KEDALAMAN SUMUR = 4 M BERISI 8 BETON BES
HARGA 1 BETON BES =RP.50.000 X 8 BETON BES = RP.400.000
Ø HARGA 1 BUAH WASTAVEL = RP.400.000
Ø HARGA 1 BUAH WASTAVEL = RP.400.000
Ø HARGA POMPA AIR MERK NASIONAL = RP.400.000
Ø PIPA 4**/400 = RP.50.000 X 8 BARTANG = RP.400.000
Ø PIPA 3/4** /400 = RP.20.000 X 5 BATANG = RP.100.000
Ø PIPA 1** /400 = RP.30.000 X 1 BATANG = RP.30.000
Ø SAMBUNGAN ELBOW 4** = RP.4000 X 8 = RP.32.000
Ø SAMBUNGAN ELBOW 3/4** = RP.5000 X 7 = RP.35.000
Ø SAMBUNGAN ELBOW 1** = RP.4000 X 2 = RP.8000
Ø SAMBUNGAN Tee ¾** = RP.4000 X 2 = RP.8000
Ø SAMBUNGAN Tee 4** = RP.4000 X 2 = RP.8000
Ø SAMBUNGAN VALVE SHOCKET ¾** = RP.4000 X 4 = RP.16.000
Ø SAMBUNGAN FLOCK SHOCKET ¾** = RP.4000 X 3 =RP.12.000
Ø SAMBUNGAN FLOCK SHOCKET 4** = RP.4000 X 3 = RP.12.000
Ø MEMBUTUHKAN 4 KRAN X RP.10.000 = RP.40.000
Ø MEMBUTUHKAN 10 SELOTIP X RP.2000 = RP.20.000
Ø MEMBUTUHKAN 3 LEM PEREKAT X RP.10.000 = RP.30.000
Ø DIKERJAKAN 2 TUKANG X RP.60.000 X 14 HARI = RP.1.680.000
Ø DIKERJAKAN 2 KULI X RP.50.000 X 14 HARI = RP.1.400.000+
RP.6.581.000
Ø BIAYA TAK TERDUGA 10% X RP.6.581.000 = RP.658.100
v TOTAL = RP.7.239.100
REKAPITULASI BIAYA
Ø BIAYA PKERJAAN PONDASI = RP.13.332.000
Ø BIAYA PEKERJAAN DINDING = RP.23.750.760
Ø BIAYA RENCANA ATAP DAN KUDA KUDA = RP.36.338.500
Ø BIAYA RENCANA TERAS ,PLAT,INTERNIT = RP.13.491.500
Ø BIAYA PEMBUATAN KUSEN = RP.15.800.000
Ø BIAYA RENCANA UBIN = RP.6.545.000
Ø BIAYA PENGECATAN = RP.4.026.000
Ø BIAYA SALURAN AIR BERSIH DAN KOTOR = RP.7.239.100+
vTOTAL = RP.120.522.860